To stabilize a sinking garage foundation, we use Helical Pier Systems to transfer the structural weight of the garage away from failing surface soils and down to deeper, load-bearing strata. This process provides permanent stability where shallow soils can no longer support the structure.
The installation follows a precise professional sequence:
- Site Preparation and Excavation: We expose the existing footing, typically excavating 3 to 4 feet deep to reach the base of the foundation.
- Strategic Positioning: Using compact equipment that requires as little as four feet of headroom, we position the helical lead section under the footing.
- Hydraulic Rotation: We drive the pier shaft into the ground using hydraulic rotation. During this phase, we utilize real-time torque monitoring to verify that each pier reaches the exact engineered load specification required for your specific site.
- Bracket Attachment: Once the pier reaches the target torque value and depth, an underpinning repair bracket is secured to the pier and the existing concrete footing.
- Lift and Load Transfer: Using hydraulic equipment, the foundation is raised back to its correct level according to engineering plans. The structural load is then transferred through the brackets onto the piers.
This method is highly efficient as it avoids the long curing times associated with traditional concrete repairs. Because we adhere to ICC-ES AC358 standards, you can be confident that the repair is both safe and compliant with building codes.
Note: Before beginning, it is essential to consult a structural engineer. Through our network of structural engineers and Engineering Excellence and Design Support, we can help you obtain the required soil evaluations and load calculations to ensure a successful repair.
Related FAQs
-
What are the Standard Methods for Testing Helical Pile Load Capacity?
Read More »: What are the Standard Methods for Testing Helical Pile Load Capacity?Standard methods for testing helical pile load capacity primarily include direct measurement through static load testing and empirical estimation via torque correlation. These methods ensure that installed piles meet design specifications and building code requirements. Static Load Testing (ASTM D1143):…
-
Why is Pile Load Testing Required for Commercial Construction Projects?
Read More »: Why is Pile Load Testing Required for Commercial Construction Projects?For commercial construction projects, pile load testing is a non-negotiable quality assurance requirement primarily driven by safety, design validation, and legal mandates. Key reasons for requiring these tests include: Design Validation: Load testing is the only definitive way to verify…
-
What is the Difference between End-bearing Piles and Friction Piles in Commercial Design?
Read More »: What is the Difference between End-bearing Piles and Friction Piles in Commercial Design?In commercial pile foundation design, the primary difference between end-bearing piles and friction piles lies in how they transfer structural loads to the subsurface soil. The choice between them depends on the site’s soil stratigraphy and the depth of competent…
-
How Much do Helical Piers Cost per Foot Installed?
Read More »: How Much do Helical Piers Cost per Foot Installed?Based on the provided documentation, there is no flat price per foot for helical pier installation. The total cost is determined by several site-specific variables rather than a standard linear measurement. Because every project requires unique structural calculations and soil…
-
How do Foundation Contractors Estimate Helical Pier Project Costs?
Read More »: How do Foundation Contractors Estimate Helical Pier Project Costs?Foundation contractors estimate helical pier project costs by evaluating several site-specific variables rather than using a flat rate. Because every project has unique structural and geological demands, contractors typically use a custom-quote process that considers the following primary cost drivers:…